  1. Management reserves is controlled by who? and not who?
    Managemnt, not PM
  2. _____________ is for unknown unknowns and unplaned changes to project scope or cost.
    Management Reserves
  3. ___________ is for known unknowns and additional cost time estimating and risk.
    contingency reserve
  4. ---------------- is using information from similar projects done in the past.  Top down estimating.
    Analogous Estimating
  5. A change request must always be written and never ___________
    verbal
  6. If a change happens that involves funds always contact who?
    The sponsor
  7. __________ sometimes called cost center is associated with the WBS.
    Control Point
  8. the _____________ contains
    SOW
    Planned Duration
    Budget
    Responsibility Requirements
    Specs
    Acceptance Criteria
    Contract Info
    Dependencies
    WBS Dictionary
  9. ___________________ is an manageable unit of work that can be planned, controlled, budgeted and scheduled as individual entities.
    Work Package
  10. A work package must be ________ enough to make realistic estimates but not to small to overwhelpl the planning and control process.
    small
  11. Only involve the sponser when the problem involves ____________ and _____________
    money, budger
  12. Cost of change goes __________ as you get further along in the project.
    Up
  13. All changes go through ___________ process but not necessarily through Change control board.
    Change Control
  14. ____________ project should always have a change control board. Smaller projects the decisions can be made by ____________, __________________, or _____________
    Large, Sponsor, stakeholder, project manager.

Card Set Information

Author:
DSWare
ID:
225262
Filename:
PMP
Updated:
2013-06-28 06:38:17
Tags:
PMP
Folders:

Description:
PMP Exam
Show Answers:

What would you like to do?

Home > Flashcards > Print Preview