  1. What document lists stakeholders and relevant details for each?
    STakeholder Register
  2. What outlines strategies for managing various stakeholders expectations/involvement?
    Stakeholder Management Plan
  3. What tracks disagreements and/or unresolved matters and outlines plan for resolving?
    Issues Log
  4. What shows all changes made during a project along with their impact on various constraints?
    Change Log
  5. What are ways of predicting/assessing potential outcomes in light of various project variables?
    Analytical Techiniques
  6. What are the 4 Processes for Project Stakeholder Management and what process group are they in?
    • 1. Identify Stakeholders - Initiating
    • 2. Plan Stakeholder Managementt - Planning
    • 3. Manage Stakeholder Engagement - Executing
    • 4. Control Stakeholder Engagement - Monitoring & Control
  7. What are the 4 inputs for the Identify Stakeholders Process?
    • 1. Project Charter
    • 2. Procurement documents
    • 3. Enterprise environmental factors
    • 4. Organizational process assets
  8. What are the 3 tools/Techniques for the Identify Stakeholders Process?
    • 1. Stakeholder analysis
    • 2. Expert judgment
    • 3. Meetings
  9. What is the output for the Identify Stakeholders Process?
    1. Stakeholder Register
  10. What are the 4 inputs for the Plan Stakeholder Management Process?
    • 1. Project Mgmt plan
    • 2. Stakeholder register
    • 3. Enterprise environmental factors
    • 4. Organizational process assets
  11. What are the 3 Tools/techniques for the Plan Stakeholder Management Process?
    • 1. Expert judgement
    • 2. Meetings
    • 3. Analytical techniques
  12. What are the 2 outputs for the Plan Stakeholder Management Process?
    • 1. Stakeholder management Plan
    • 2. Project documents updates
  13. What are the 4 inputs to the Manage Stakeholder Engagement process?
    • 1. Stakeholder Mgmt plan
    • 2. Communications mgmt plan
    • 3. Change log
    • 4. Organizational process assets
  14. What are the 3 tools/techniques for the Manage Stakeholder Engagement process?
    • 1. Communication methods
    • 2. Interpersonal skills
    • 3. Management skills
  15. What are the 5 outputs for the the Manage Stakeholder Engagement process?
    • 1. Issue Log
    • 2. Change requests
    • 3. Project management plan updates
    • 4. Project documents updates
    • 5. Organizational process assets updates
  16. What are the 4 inputs to the Control Stakeholder Engagement Process?
    • 1. Project Management Plan
    • 2. Issue Log
    • 3. Work Performance Data
    • 4. Project documents
  17. What are the 3 tools/techniques for the Control Stakeholder Engagement Process?
    • 1. Information management systems
    • 2. Expert judgement
    • 3. Meetings
  18. What are the 5 outputs for  the Control Stakeholder Engagement Process?
    • 1. Work performance info
    • 2. Change requests
    • 3. Project mgmt plan updates
    • 4. Project documents updates
    • 5. Organizational process assets updates