  1. What is the formula to calculate variance?
    Standard Deviation Squared SD2
  2. What is the formula used to calculate Activity Variance
    [(P-O)/6]2

    • P = Pessimistic
    • O = Optomistic
  3. Quality should be checked before an activity or work package is completed.
    TRUE
  4. Project definition
    - temporary endeavor with a beginning and an end

    - creates a unique product, service, or result
  5. Process Groups
    • - Initiating
    • - Planning
    • - Executing
    • - Monitoring and Controlling
    • - Closing
  6. Knowledge Areas
    • - PM Framework
    • - PM Processes
    • - Integration
    • - Scope
    • - Time
    • - Cost
    • - Quality
    • - Human Resources
    • - Communications
    • - Risk
    • - Proceurement Management
  7. Functional Organization Form - Advantages and Disadvantages
    • Advantages:
    • - Easier management of specialists
    • - Team members report to only one supervisor
    • - Similiar resources are centralized, as the company is grouped by specialists
    • - Clearly defined career paths in areas of work specialization

    • Disadvantages
    • - People place more emphasis on their functional speciality to the detriment of the project
    • - No career path in project management
    • - The project manager has little or no authority
  8. Projectized Organizational Form - Advantages and Disadvantages
    • Advantages:
    • - Efficient proejct organization
    • - Loyalty to the project
    • - More effective communications than functional

    • Disadvantages
    • - No 'home' when project is completed
    • - Lack of professionalism in disciplines
    • - Duplication of facilities and job functions
    • - Less efficient use of resources
  9. Matrix Organizational Form - Advantages and Disadvantages
    • Advantages
    • - Highly visible project objectives
    • - Improved project manager control over resources
    • - More support from functional areas
    • - Maximum utilization of scarce resources
    • - Better coordination
    • - Better horizontal and vertical dissemination of information
    • - Team members maintain a 'home'

    • Disadvantages:
    • - Extra administration is required
    • - More than one boss for project teams
    • - More complex to monitor and control
    • - Tougher problems with resource allocation
    • - Need extensive policies and procedures
    • - Functional managers may have different priorities than project managers
    • - Higher potential for conflict