  1. You are the project manager of the HGF Project.  You would like touse a portion of the activity list from the HGB Project, which is similar toyour current project.  The portion of the activity list from the HGB Project is best described as which of the following:

    A. Rolling Wave planning
    B. A Template
    C. Expert Judgement
    D. Analogous estimating
    B. A Template
    (this multiple choice question has been scrambled)
  2. Mary has created an activity list with her project team. She has included activity attributes for each of the activities in her project activity list.  Of the following which one is not an example of an activity attribute that Mary likely included?

    A. Scope verification process
    B. Predecessor activities
    C. leads & lags
    D. geographic area where the work must take place
    A. scope verification
    (this multiple choice question has been scrambled)
  3. Your project team agrees that the server operating system must first be installed before the application can be installed.  This best describes which one of the following?

    A. finish-to-finish relationship
    B. start-to-start relationship
    C. hard logic
    D. soft logic
    C. hard logic
    (this multiple choice question has been scrambled)