  1. You are the project manager of the HGF Project.  You would like touse a portion of the activity list from the HGB Project, which is similar toyour current project.  The portion of the activity list from the HGB Project is best described as which of the following:

    A. Analogous estimating
    B. A Template
    C. Rolling Wave planning
    D. Expert Judgement
    B. A Template
    (this multiple choice question has been scrambled)
  2. Mary has created an activity list with her project team. She has included activity attributes for each of the activities in her project activity list.  Of the following which one is not an example of an activity attribute that Mary likely included?

    A. leads & lags
    B. geographic area where the work must take place
    C. Predecessor activities
    D. Scope verification process
    D. scope verification
    (this multiple choice question has been scrambled)
  3. Your project team agrees that the server operating system must first be installed before the application can be installed.  This best describes which one of the following?

    A. soft logic
    B. hard logic
    C. finish-to-finish relationship
    D. start-to-start relationship
    B. hard logic
    (this multiple choice question has been scrambled)