  1. What planning step comes before “Create network diagram”?
    Create activity list
  2. What planning step comes before “Prepare procurement documents”?
    Go back-iterations
  3. What planning step comes before “Create project scope statement”?
    Finalize requirements
  4. What planning step comes before “Create WBS and WBS dictionary”?
    Determine team
  5. What planning step comes before “Determine critical path”?
    Estimate time and cost
  6. What planning step comes before “Develop budget”?
    Develop schedule
  7. What planning step comes before “Estimate time and cost”?
    Estimate resource requirements
  8. What planning step comes before “Gain formal approval of the plan”?
    Develop final project management plan and a performance measurement baseline that are realistic
  9. What planning step comes before “Hold kickoff meeting”?
    Gain formal approval of the plan
  10. What planning step comes before “Determine quality standards, processes, and metrics”?
    Develop budget
  11. What planning step comes before “Determine what to purchase”?
    Create project scope statement
  12. What planning step comes before “Plan communications”?
    Determine all roles and responsibilities
  13. What planning step comes before “Go back-iterations”?
    Perform risk identification, qualitative and quantitative risk analysis, and risk response planning
  14. What planning step comes before “Create process improvement plan”?
    Determine quality standards, processes, and metrics
  15. What planning step comes before “Determine all roles and responsibilities”?
    Create process improvement plan
  16. What planning step comes before “Perform risk identification, qualitative and quantitative risk analysis, and risk response planning”?
    Plan communications
  17. What planning step comes before “Estimate resource requirements”?
    Create network diagram
  18. What planning step comes before “Create activity list”?
    Create WBS and WBS dictionary