  1. Create measurable objectives: belongs to process group?

    A) Closing
    B) Executing
    C) Monitoring & Controlling
    D) Planning
    E) Initiating
    E)
    (this multiple choice question has been scrambled)
  2. Determine how you will do planning-part of all management plans: belongs to process group?

    A) Initiating
    B) Monitoring & Controlling
    C) Planning
    D) Closing
    E) Executing
    C)
    (this multiple choice question has been scrambled)
  3. Administer procurements: belongs to process group?

    A) Initiating
    B) Monitoring & Controlling
    C) Planning
    D) Closing
    E) Executing
    B)
    (this multiple choice question has been scrambled)
  4. Execute the work according to the PM plan: belongs to process group?

    A) Executing
    B) Initiating
    C) Closing
    D) Monitoring & Controlling
    E) Planning
    A)
    (this multiple choice question has been scrambled)
  5. Determine company culture and existing systems: belongs to process group?

    A) Closing
    B) Executing
    C) Monitoring & Controlling
    D) Initiating
    E) Planning
    D)
    (this multiple choice question has been scrambled)
  6. Perform quality assurance: belongs to process group?

    A) Initiating
    B) Planning
    C) Executing
    D) Monitoring & Controlling
    E) Closing
    C)
    (this multiple choice question has been scrambled)
  7. Create activity list: belongs to process group?

    A) Planning
    B) Initiating
    C) Closing
    D) Executing
    E) Monitoring & Controlling
    A)
    (this multiple choice question has been scrambled)
  8. Go back-iterations: belongs to process group?

    A) Initiating
    B) Closing
    C) Monitoring & Controlling
    D) Planning
    E) Executing
    D)
    (this multiple choice question has been scrambled)
  9. Develop project charter: belongs to process group?

    A) Monitoring & Controlling
    B) Closing
    C) Initiating
    D) Planning
    E) Executing
    C)
    (this multiple choice question has been scrambled)
  10. Develop schedule: belongs to process group?

    A) Initiating
    B) Closing
    C) Planning
    D) Monitoring & Controlling
    E) Executing
    C)
    (this multiple choice question has been scrambled)
  11. Use the work authorization system: belongs to process group?

    A) Executing
    B) Monitoring & Controlling
    C) Initiating
    D) Planning
    E) Closing
    A)
    (this multiple choice question has been scrambled)
  12. Measure performance against other metrics determined by the project manager: belongs to process group?

    A) Monitoring & Controlling
    B) Initiating
    C) Planning
    D) Executing
    E) Closing
    A)
    (this multiple choice question has been scrambled)
  13. Collect processes, procedures, and historical information: belongs to process group?

    A) Executing
    B) Monitoring & Controlling
    C) Initiating
    D) Closing
    E) Planning
    C)
    (this multiple choice question has been scrambled)
  14. Hand off completed product: belongs to process group?

    A) Closing
    B) Planning
    C) Executing
    D) Initiating
    E) Monitoring & Controlling
    A)
    (this multiple choice question has been scrambled)
  15. Determine team: belongs to process group?

    A) Closing
    B) Monitoring & Controlling
    C) Executing
    D) Initiating
    E) Planning
    E)
    (this multiple choice question has been scrambled)
  16. Request changes: belongs to process group?

    A) Closing
    B) Planning
    C) Monitoring & Controlling
    D) Initiating
    E) Executing
    C)
    (this multiple choice question has been scrambled)
  17. Index and archive records: belongs to process group?

    A) Planning
    B) Initiating
    C) Monitoring & Controlling
    D) Executing
    E) Closing
    E)
    (this multiple choice question has been scrambled)
  18. Determine variances and if they warrant a change request: belongs to process group?

    A) Monitoring & Controlling
    B) Planning
    C) Executing
    D) Closing
    E) Initiating
    A)
    (this multiple choice question has been scrambled)
  19. Gain formal acceptance of the product: belongs to process group?

    A) Planning
    B) Monitoring & Controlling
    C) Initiating
    D) Closing
    E) Executing
    D)
    (this multiple choice question has been scrambled)
  20. Create WBS and WBS dictionary: belongs to process group?

    A) Planning
    B) Closing
    C) Executing
    D) Monitoring & Controlling
    E) Initiating
    A)
    (this multiple choice question has been scrambled)
  21. Implement only approved changes: belongs to process group?

    A) Executing
    B) Planning
    C) Closing
    D) Initiating
    E) Monitoring & Controlling
    A)
    (this multiple choice question has been scrambled)
  22. Take action to control the project: belongs to process group?

    A) Closing
    B) Executing
    C) Initiating
    D) Monitoring & Controlling
    E) Planning
    D)
    (this multiple choice question has been scrambled)
  23. Estimate time and cost: belongs to process group?

    A) Executing
    B) Monitoring & Controlling
    C) Planning
    D) Closing
    E) Initiating
    C)
    (this multiple choice question has been scrambled)
  24. Create network diagram: belongs to process group?

    A) Planning
    B) Closing
    C) Initiating
    D) Monitoring & Controlling
    E) Executing
    A)
    (this multiple choice question has been scrambled)
  25. Manage people: belongs to process group?

    A) Planning
    B) Monitoring & Controlling
    C) Initiating
    D) Executing
    E) Closing
    D)
    (this multiple choice question has been scrambled)
  26. Evaluate team and project performance: belongs to process group?

    A) Initiating
    B) Closing
    C) Planning
    D) Executing
    E) Monitoring & Controlling
    D)
    (this multiple choice question has been scrambled)
  27. Inform stakeholders of approved changes: belongs to process group?

    A) Closing
    B) Monitoring & Controlling
    C) Initiating
    D) Planning
    E) Executing
    B)
    (this multiple choice question has been scrambled)
  28. Influence the factors that cause changes: belongs to process group?

    A) Executing
    B) Closing
    C) Monitoring & Controlling
    D) Initiating
    E) Planning
    C)
    (this multiple choice question has been scrambled)
  29. Divide large projects into phases: belongs to process group?

    A) Initiating
    B) Closing
    C) Monitoring & Controlling
    D) Executing
    E) Planning
    A)
    (this multiple choice question has been scrambled)
  30. Understand the business case: belongs to process group?

    A) Monitoring & Controlling
    B) Planning
    C) Executing
    D) Initiating
    E) Closing
    D)
    (this multiple choice question has been scrambled)
  31. Produce product scope: belongs to process group?

    A) Planning
    B) Closing
    C) Initiating
    D) Monitoring & Controlling
    E) Executing
    E)
    (this multiple choice question has been scrambled)
  32. Request changes: belongs to process group?

    A) Closing
    B) Monitoring & Controlling
    C) Executing
    D) Planning
    E) Initiating
    B)
    (this multiple choice question has been scrambled)
  33. Perform quality audits: belongs to process group?

    A) Initiating
    B) Executing
    C) Closing
    D) Monitoring & Controlling
    E) Planning
    B)
    (this multiple choice question has been scrambled)
  34. Uncover requirements and initial risks: belongs to process group?

    A) Monitoring & Controlling
    B) Planning
    C) Closing
    D) Executing
    E) Initiating
    E)
    (this multiple choice question has been scrambled)
  35. Estimate resource requirements: belongs to process group?

    A) Planning
    B) Initiating
    C) Executing
    D) Monitoring & Controlling
    E) Closing
    A)
    (this multiple choice question has been scrambled)
  36. Determine quality standards, processes, and metrics: belongs to process group?

    A) Planning
    B) Executing
    C) Monitoring & Controlling
    D) Initiating
    E) Closing
    A)
    (this multiple choice question has been scrambled)
  37. Use issue logs: belongs to process group?

    A) Initiating
    B) Planning
    C) Closing
    D) Executing
    E) Monitoring & Controlling
    D)
    (this multiple choice question has been scrambled)
  38. Perform integrated change control: belongs to process group?

    A) Planning
    B) Monitoring & Controlling
    C) Executing
    D) Initiating
    E) Closing
    B)
    (this multiple choice question has been scrambled)
  39. Create process improvement plan: belongs to process group?

    A) Planning
    B) Closing
    C) Monitoring & Controlling
    D) Executing
    E) Initiating
    A)
    (this multiple choice question has been scrambled)
  40. Identify stakeholders: belongs to process group?

    A) Monitoring & Controlling
    B) Executing
    C) Closing
    D) Planning
    E) Initiating
    E)
    (this multiple choice question has been scrambled)
  41. Determine critical path: belongs to process group?

    A) Closing
    B) Executing
    C) Planning
    D) Initiating
    E) Monitoring & Controlling
    C)
    (this multiple choice question has been scrambled)
  42. Release resources: belongs to process group?

    A) Closing
    B) Monitoring & Controlling
    C) Executing
    D) Planning
    E) Initiating
    A)
    (this multiple choice question has been scrambled)
  43. Develop stakeholder management strategy: belongs to process group?

    A) Executing
    B) Monitoring & Controlling
    C) Planning
    D) Initiating
    E) Closing
    D)
    (this multiple choice question has been scrambled)
  44. Perform quality control: belongs to process group?

    A) Initiating
    B) Closing
    C) Executing
    D) Monitoring & Controlling
    E) Planning
    D)
    (this multiple choice question has been scrambled)
  45. Plan communications: belongs to process group?

    A) Initiating
    B) Executing
    C) Closing
    D) Monitoring & Controlling
    E) Planning
    E)
    (this multiple choice question has been scrambled)
  46. Perform risk identification, qualitative and quantitative risk analysis, and risk response planning: belongs to process group?

    A) Closing
    B) Initiating
    C) Executing
    D) Planning
    E) Monitoring & Controlling
    D)
    (this multiple choice question has been scrambled)
  47. Gain formal approval of the plan: belongs to process group?

    A) Initiating
    B) Closing
    C) Monitoring & Controlling
    D) Executing
    E) Planning
    E)
    (this multiple choice question has been scrambled)
  48. Facilitate conflict resolution: belongs to process group?

    A) Closing
    B) Initiating
    C) Monitoring & Controlling
    D) Planning
    E) Executing
    E)
    (this multiple choice question has been scrambled)
  49. Approve or reject changes: belongs to process group?

    A) Initiating
    B) Closing
    C) Planning
    D) Executing
    E) Monitoring & Controlling
    E)
    (this multiple choice question has been scrambled)
  50. Hold kickoff meeting: belongs to process group?

    A) Executing
    B) Planning
    C) Monitoring & Controlling
    D) Initiating
    E) Closing
    B)
    (this multiple choice question has been scrambled)
  51. Ensure common understanding: belongs to process group?

    A) Executing
    B) Initiating
    C) Planning
    D) Closing
    E) Monitoring & Controlling
    A)
    (this multiple choice question has been scrambled)
  52. Prepare procurement documents: belongs to process group?

    A) Closing
    B) Planning
    C) Monitoring & Controlling
    D) Executing
    E) Initiating
    B)
    (this multiple choice question has been scrambled)
  53. Hold team-building activities: belongs to process group?

    A) Executing
    B) Closing
    C) Planning
    D) Initiating
    E) Monitoring & Controlling
    A)
    (this multiple choice question has been scrambled)
  54. Send and receive information: belongs to process group?

    A) Executing
    B) Monitoring & Controlling
    C) Initiating
    D) Closing
    E) Planning
    A)
    (this multiple choice question has been scrambled)
  55. Finalize the "how to execute and control" parts of all management plans: belongs to process group?

    A) Planning
    B) Closing
    C) Initiating
    D) Executing
    E) Monitoring & Controlling
    A)
    (this multiple choice question has been scrambled)
  56. Give recognition and rewards: belongs to process group?

    A) Planning
    B) Monitoring & Controlling
    C) Executing
    D) Closing
    E) Initiating
    C)
    (this multiple choice question has been scrambled)
  57. Continuously improve: belongs to process group?

    A) Monitoring & Controlling
    B) Executing
    C) Initiating
    D) Planning
    E) Closing
    B)
    (this multiple choice question has been scrambled)
  58. Develop final PM plan and performance measurement baseline that are realistic: belongs to process group?

    A) Closing
    B) Initiating
    C) Monitoring & Controlling
    D) Planning
    E) Executing
    D)
    (this multiple choice question has been scrambled)
  59. Determine all roles and responsibilities: belongs to process group?

    A) Monitoring & Controlling
    B) Initiating
    C) Closing
    D) Planning
    E) Executing
    D)
    (this multiple choice question has been scrambled)
  60. Follow processes: belongs to process group?

    A) Monitoring & Controlling
    B) Executing
    C) Closing
    D) Initiating
    E) Planning
    B)
    (this multiple choice question has been scrambled)
  61. Develop budget: belongs to process group?

    A) Planning
    B) Executing
    C) Initiating
    D) Closing
    E) Monitoring & Controlling
    A)
    (this multiple choice question has been scrambled)
  62. Gain acceptance of interim deliverables from the customer: belongs to process group?

    A) Planning
    B) Monitoring & Controlling
    C) Closing
    D) Initiating
    E) Executing
    B)
    (this multiple choice question has been scrambled)
  63. Create forecasts: belongs to process group?

    A) Initiating
    B) Executing
    C) Monitoring & Controlling
    D) Closing
    E) Planning
    C)
    (this multiple choice question has been scrambled)
  64. Hold meetings: belongs to process group?

    A) Monitoring & Controlling
    B) Planning
    C) Closing
    D) Executing
    E) Initiating
    D)
    (this multiple choice question has been scrambled)
  65. Complete procurement closure: belongs to process group?

    A) Closing
    B) Monitoring & Controlling
    C) Executing
    D) Initiating
    E) Planning
    A)
    (this multiple choice question has been scrambled)
  66. Perform risk audits: belongs to process group?

    A) Closing
    B) Monitoring & Controlling
    C) Executing
    D) Initiating
    E) Planning
    B)
    (this multiple choice question has been scrambled)
  67. Select sellers: belongs to process group?

    A) Planning
    B) Monitoring & Controlling
    C) Closing
    D) Initiating
    E) Executing
    E)
    (this multiple choice question has been scrambled)
  68. Manage configuration: belongs to process group?

    A) Closing
    B) Monitoring & Controlling
    C) Executing
    D) Initiating
    E) Planning
    B)
    (this multiple choice question has been scrambled)
  69. Manage reserves: belongs to process group?

    A) Planning
    B) Closing
    C) Executing
    D) Monitoring & Controlling
    E) Initiating
    D)
    (this multiple choice question has been scrambled)
  70. Measure performance against the performance measurement baseline: belongs to process group?

    A) Monitoring & Controlling
    B) Initiating
    C) Executing
    D) Closing
    E) Planning
    A)
    (this multiple choice question has been scrambled)
  71. Confirm work is done to requirements: belongs to process group?

    A) Initiating
    B) Executing
    C) Monitoring & Controlling
    D) Planning
    E) Closing
    E)
    (this multiple choice question has been scrambled)
  72. Report on project performance: belongs to process group?

    A) Closing
    B) Executing
    C) Initiating
    D) Monitoring & Controlling
    E) Planning
    D)
    (this multiple choice question has been scrambled)
  73. Acquire final team: belongs to process group?

    A) Initiating
    B) Executing
    C) Planning
    D) Closing
    E) Monitoring & Controlling
    B)
    (this multiple choice question has been scrambled)
  74. Finalize requirements: belongs to process group?

    A) Monitoring & Controlling
    B) Planning
    C) Closing
    D) Executing
    E) Initiating
    B)
    (this multiple choice question has been scrambled)
  75. Determine what to purchase: belongs to process group?

    A) Planning
    B) Monitoring & Controlling
    C) Executing
    D) Closing
    E) Initiating
    A)
    (this multiple choice question has been scrambled)
  76. Complete final performance reporting: belongs to process group?

    A) Planning
    B) Monitoring & Controlling
    C) Closing
    D) Initiating
    E) Executing
    C)
    (this multiple choice question has been scrambled)
  77. Select project manager: belongs to process group?

    A) Executing
    B) Initiating
    C) Monitoring & Controlling
    D) Closing
    E) Planning
    B)
    (this multiple choice question has been scrambled)
  78. Create project scope statement: belongs to process group?

    A) Closing
    B) Planning
    C) Initiating
    D) Monitoring & Controlling
    E) Executing
    B)
    (this multiple choice question has been scrambled)
  79. Update lessons learned knowledge base: belongs to process group?

    A) Executing
    B) Initiating
    C) Planning
    D) Monitoring & Controlling
    E) Closing
    E)
    (this multiple choice question has been scrambled)

What would you like to do?

Home > Flashcards > Print Preview