Rigging Pre-Lift Planning

Card Set Information

Author:
clainez27
ID:
260955
Filename:
Rigging Pre-Lift Planning
Updated:
2014-02-08 23:55:59
Tags:
Pre lift Planning
Folders:

Description:
Rigging Pre Lift Planning
Show Answers:

Home > Flashcards > Print Preview

The flashcards below were created by user clainez27 on FreezingBlue Flashcards. What would you like to do?


  1. All lift plans are complex and require an engineering staff and a site drawing.
    True or False?
    False
  2. A documented pre-lift plan will state the names of the engineers and supervisors who have worked to prepare the plan.true or false?
    True
  3. There are standardized industry rules to specify what is classified as a crucial lift.
    True or False?
    False
  4. Which of the following would be classed as a critical lift?
    A. operating over or near powerlines
    B. two cranes working in tandem
    C. The load is close to the crane's capacities
    D. All of the above
    D. All of the above
  5. Any load heavier than 75% of the rated capacity of a crane is a critical lift . True or False?
    True
  6. A print or drawing of a lift never includes actual measurements or distances as they are usually too hard to calculate until the crane is hooked to the load.True or False?
    False
  7. A detailed print or drawing of a lift eliminates guesswork. True or False?
    True
  8. If a crane can sit firmly without the tracks or outriggers sinking into the ground prior to lifting the load, a soil analysis is never needed. true or false?
    False
  9. On, a critical lift, It is necessary that the load radius, boom length, and boom angle are known when hooking up the load.True or False?
    True
  10. Using the crane load indicator as a scale to weigh a load is an accepted practice when preparing a lift plan. True or False?
    False
  11. Which of the following is the most satisfactory method of signaling on a two-crane lift?
    A. One person using hand signals for both cranes.
    B. One person using Voice communication
    C. One person using hand signals for each crane
    B. One person using voice communication
    (this multiple choice question has been scrambled)
  12. As the pre-lift items that must be investigated by a planning group are completed, the results are entered and filed in a series of:
    A. crane log books
    B. checklists
    C. crane maintenance manuals
    D. Inter-office memos
    B. checklists
    (this multiple choice question has been scrambled)