carpentry 1- foundation forms and concrete

The flashcards below were created by user heeres on FreezingBlue Flashcards.

  1. what is a material takeoff?
    an itemized list of all of the materials required to complete a specific job.
  2. what is an estimate?
    an educated guess based on past experience to price out a job
  3. when should you always round up to the next 1/4m³?
    when ordering concrete
  4. how is the concrete for a basement floor calculated?
    floor area × slab thickness