Home > Flashcards > Print Preview

The flashcards below were created by user egf4201 on FreezingBlue Flashcards. What would you like to do?


  1. Who is responsible to ensure that all of the requirements of API 510 are met?
    owner/ user
  2. Who is responsible to ensure that the authorized inspection agency functions in accordance with the requirements of API 510?
    owner/user
  3. each owner/user that uses API 510 must
    maintain a quality assurance inspection manual
  4. which of the following is not required to be in the owner/user's quality assurance inspection manual?
    A) establish vacation policy for authorized inspectors
    B) directions on how to document inspection results
    C) Specify approval process for calculations perfomed during vessel alterations
    D) calibration of NDE equipment
    E) Training requirements for inspection personnel
    A) establish vacation policy for authorized inspectors
    (this multiple choice question has been scrambled)
  5. Which of the following is not a role for the API 510 inspector?
    A) Provide the owner assurance that all welding meet requirements
    B) provide the owner assurance that all pressure testing meet requirements
    C) provide the owner assurance that all NDE examinations meet requirements
    D) provide the owner assurance that all inspections meet requirements
    A) Provide the owner assurance that all welding meet requirements
    (this multiple choice question has been scrambled)
  6. during in-service vessel repairs. all examination results must be accepted by the
    authorized inspector
  7. Which of the following is a role for the API 510 inspector?
    A) evaluate and accept NDE results
    B) autorize substitution of pre-heat in lieu of PWHT during vessel repairs
    C) Provide solutions when welding problems occur
    D) train on site NDE personnel 
    A) evaluate and accept NDE results
    (this multiple choice question has been scrambled)
  8. When repairs and alterations are being conducted, which individual or organization is responsible for Q.C.
    repair organization
  9. when repairs and alterations are being conducted, which individual or organization is responsible for validating that the materials meet the requirements of API 510
    Repair organization
  10. when NDE is performed on in service vessels, who must maintain a record of the NDE personnel certification
    Employer