Earned Value Formula

Card Set Information

Author:
kwilliamsmba08
ID:
92907
Filename:
Earned Value Formula
Updated:
2011-07-04 14:00:28
Tags:
Earned Value Formula kwilliamsmba08
Folders:

Description:
Earned Value Formula
Show Answers:

Home > Flashcards > Print Preview

The flashcards below were created by user kwilliamsmba08 on FreezingBlue Flashcards. What would you like to do?


  1. PV
    Planned Value
  2. EV
    Earned Value
  3. AC
    Actual Cost
  4. SV
    • Schedule Variance
    • EV-PV
  5. CV
    • Cost Variance
    • EV-AC
  6. CPI
    • Cost Performance Index
    • EV/AC
  7. SPI
    • Schedule Performance Index
    • EV/PV
  8. EAC
    1. Eastimate assumptions not valid
    2. Current Variances are atypical
    3. Current Variances are typical
    • Eastimate at Cost completion
    • 1. AC+ETC
    • 2. AC+BAC-EV
    • 3. BAC/CPI or AC+{(BAC-EV)}/CPI}
  9. ETC
    • Estimate To Complete
    • EAC-AC
  10. % to complete Percentage to complete
    (EV/BAC)X100
  11. VAC
    • Variance at completion
    • BAC-EAC
  12. TCPI Time to complete Performance Index
    1. (Based on BAC)
    2. (Based on EAC)
    • 1. (BAC-EV)/(BAC-AC)
    • 2. (BAC-EV)/(EAC-AC)